Confidential
Proceedings under the ICC rules between a French general contractor and a Brazilian subcontractor regarding a powerline construction project in Ethiopia.
Proceedings under the ICC rules between a French general contractor and a Brazilian subcontractor regarding a powerline construction project in Ethiopia.
Advised Ecuadorian company in an arbitration with a Swiss company under the Rules of the Guayaquil Chamber of Commerce.
Proceedings under the UNCITRAL rules, administered by the PCA, between a US consortium and a Costa Rican State-owned electricity company (chair of the tribunal).
Two proceedings under the ICC rules related to the construction of two separate prison complexes in Argentina.
Counsel to Venezuela in an annulment proceeding in a dispute that arose out of the alleged expropriation of the interests of the investor in a nitrogen-based fertilizer producer company.
Represented a Bolivian instrumentality and the State in a dispute in two related ICC arbitrations with an Indian mining company regarding rights related to a mining concession in Bolivia. After successfully defending the instrumentality’s decision to execute one of the guarantees, we advised on the successful set aside of the portion of the award that invalidated the execution of the other guarantee.
Representating Venezuela in an annulment proceeding in a dispute that arose out of the alleged expropriation of a coffee company.
Representing certain claimant investors against Costa Rica in both the arbitration and judicial proceedings seeking vacatur of an interim award, relating to the expropriation of coastal real-property investments. Hired after the issuance of an interim award, we successfully obtained reconsideration of the award, resulting in millions of dollars in recovery for our clients. This is also one of the few, if only, cases to find that the time for service can be tolled under the Federal Arbitration Act.
Represented Brazilian operator of a gas power plant against a US-based contractor regarding the installation of a turbine under a EPC contract.
Counsel for Argentinean investor in securities related arbitration regarding the management of a portfolio of securities.
Representation of a hardwood flooring manufacturer in a dispute with its distributor regarding unpaid invoices, warranty claims, and ownership of a trademark. We prevailed in the arbitration then successfully confirmed the award in a decision that recognized the absence of a motion to vacate under the Panama Convention. Later, we successfully pierced the corporate veil and held one successor entity liable, as well as one of the two shareholders.
Represented Brazilian lessee of heavy equipment in a dispute regarding a leasing contract. In related court proceedings, we successfully argued that interim awards are subject to the New York and Panama Conventions, one of the first such decisions.